A supplier changed. What else has to be rechecked?
Say you're quoting 36 wall panels, and the timber supplier tells you they can't deliver. A second supplier offers cold-formed steel at a budget price. Somebody now has to decide whether the job can move forward and what has to be rechecked first. This page walks through that decision with invented inputs, so you can see what changes, what stays valid, and what still needs an answer.
- 21 items checked: 4 affected, 6 unchanged and 11 unresolved.
- The 11 unresolved items wait on 6 missing inputs held by 4 people, so the quote has no total yet.
- Change one assumption and only its dependents move: 5 items change state, 2 reopen and 14 stay as they were.
The situation
The plant's quote, Q-1042 rev B, assumed timber for 36 exterior wall panels, family WP-200, on a project called Harbor Row, Block C. Alpha Timber can't confirm the 2x6 lumber for the ship window, and Beta Steel has sent a budget quote for steel studs and track. That's the whole trigger, and it looks small. The lists below show how far it reaches, and they keep the plant's work apart from the contractor's work wherever the two are genuinely different.
Where it lands: not ready to re-issue the quote.
21 items were checked. 4 are affected, 6 are unchanged and 11 are unresolved. The 11 unresolved items wait on 6 missing inputs held by 4 people, and the quote has no total until those inputs arrive.
Three lists: what changed, what still stands, what needs an answer
Every item gets one of three labels, and a missing value never gets treated as zero or replaced by the old value. Plant items belong to the manufacturer, site items to the contractor, and shared items sit on the boundary and need both sides.
Affected · 4 of 21
- Q-01 Studs, 9 ft (plant). Timber studs become 600S162-43 steel studs. Price is from the vendor's budget sheet: indicative, valid 14 days, not firm.
- Q-02 Plates become track (plant). Three timber plates per panel become two steel tracks, per the vendor's typical detail. Price indicative; the engineer of record confirms the detail.
- Q-06 Cavity insulation (plant). The cavity is now 6 inches deep, not 5½. A 5½-inch batt would leave a half-inch gap, so the line moves to a 6-inch batt.
- S-2 Panel-to-panel and corner connections (shared). Joint locations stay where they are. The connection fastener changes from nails to screws, so the shop-drawing note changes.
Unchanged · 6 of 21
- Q-05 OSB sheathing, 7/16 in (plant). Same board, same size, same layout. How it is fastened is carried in Q-04.
- Q-07 Water-resistive barrier (WRB) membrane and tape (plant). Same membrane on the same face of the panel.
- Q-08 Window units W-3 (plant). Same unit, same size, same position (A-3). Whether it fits a thicker wall is a separate question: see S-3.
- Q-10 Packaging and shipping protection (plant). Panel face size and wrapping method are the same.
- S-6 Panel layout, grid positions and erection order (site). Panel count, grid positions and delivery order come from drawings the change does not touch.
- P-4 Water barrier and window install stations (plant). Same stations and same sequence. If a jamb extension is added (Q-09), that step is priced on its own line.
Unresolved · 11 of 21
- Q-03 Window opening framing (plant). The vendor sheet lists no header or sill members. The engineer of record has to size them before this line can be priced. Waiting on U-2 (the engineer of record).
- Q-04 Fasteners, framing and sheathing (plant). Screws replace nails. The unit price is on the vendor sheet, but the fastening schedule (type, spacing, count) has not been issued, so the quantity is unknown. Waiting on U-3 (the engineer of record).
- Q-09 Window jamb extension kit (new line) (plant). A new line, needed only if the wall is half an inch thicker. The window supplier has not said whether the standard frame covers it. Waiting on U-4 (the window supplier, asked through the estimator).
- Q-11 Factory labour allowance (plant). Built from the setup, inspection and rework assumptions (P-1 to P-3), and nobody has measured those for steel at Line 2. Waiting on U-3 (the engineer of record) and U-5 (the plant manager).
- S-1 Base anchorage to the slab (shared). The sill-plate anchors become a steel track with a different anchor detail. No detail has been issued. The contractor sets the anchors; the plant supplies the bottom member. Waiting on U-6 (the engineer of record).
- S-3 Window rough opening and flashing fit (shared). The wall is half an inch thicker, so the window frame depth and the flashing build-up need a check. Waiting on U-4 (the window supplier, asked through the estimator).
- S-4 Crane pick weight and lift plan (site). Member weights are on the vendor sheet, but the opening framing (Q-03) has no members yet, so the panel weight cannot be stated. Waiting on U-2 (the engineer of record).
- S-5 Top-of-wall elevation and floor-cassette bearing (shared). Overall panel height needs the track leg height, and the vendor sheet leaves it out. That makes it a missing input, and it should never be read as zero. Waiting on U-1 (procurement, asking the steel supplier).
- P-1 Setup, framing and sheathing cycle (plant). Steel needs a different jig and screw tools, and Line 2 has no measured steel cycle time or changeover. Waiting on U-5 (the plant manager).
- P-2 Inspection and hold point H-1 (plant). The check becomes screw spacing and edge distance, and the values to check come from the fastening schedule that has not been issued. Waiting on U-3 (the engineer of record).
- P-3 Rework allowance (plant). Steel fails in different ways, such as stripped screws and cut-length errors, and Line 2 has no history to size the allowance. Waiting on U-5 (the plant manager).
The assumption to challenge
The change request treats the steel as a drop-in. In its own words: “A 6-inch steel stud is a drop-in for a 2x6 timber stud, at the same panel thickness.”
A 2x6 is 5½ inches deep in fact, and the quoted steel web is 6 inches. So unless the vendor can supply a 5½-inch web, the wall is half an inch thicker, and anything sized to the cavity or the thickness moves with it. Revise the assumption and see exactly what moves and what doesn't.
| Item | As quoted, 6-inch steel stud | Revised, 5½-inch steel stud | What moved |
|---|---|---|---|
| Q-01 Studs, 9 ft | Affected | Unresolved (U-7) | Changes state. 5½-inch studs are not on the vendor sheet. There is no price, stock level or lead time. |
| Q-02 Plates become track | Affected | Unresolved (U-7) | Changes state. The matching 5½-inch track is not quoted either. |
| Q-06 Cavity insulation | Affected | Unchanged | Changes state. A 5½-inch web keeps the 5½-inch cavity, so the batt stands. |
| Q-09 Window jamb extension kit (new line) | Unresolved (U-4) | Unchanged | Changes state. Not needed. The wall keeps its thickness, so no line is added. |
| S-3 Window rough opening and flashing fit | Unresolved (U-4) | Unchanged | Changes state. Same wall thickness, so the same frame fit. |
| Q-03 Window opening framing | Unresolved (U-2) | Unresolved (U-2) | Reopened, still unresolved. Still no members listed. A 5½-inch depth changes what the engineer of record sizes, so the question reopens even though the answer is still missing. |
| S-4 Crane pick weight and lift plan | Unresolved (U-2) | Unresolved (U-2, U-7) | Reopened, still unresolved. Still no opening members, and the 5½-inch member weights are not on the vendor sheet either. |
5 items change state, 2 reopen and stay unresolved, and 14 of 21 stand exactly as they were, with the same status, the same amount and the same missing inputs. The revision adds one missing input, because the steel sheet quotes the 6-inch series only, and it closes the window-fit question, because the wall keeps its thickness. The quote is no closer to a total: 5 lines are open instead of 4. The revision moves the open question to the vendor and doesn't answer it.
The quote has no total
The timber baseline was $35,730.00. 7 of 11 lines are resolved: those cost $27,792.00 in the baseline and $28,058.40 after the change, a difference of +$266.40. The other 4 lines are open, so the quote total is not stated.
| Line | Baseline, timber | Status | After the change | Difference |
|---|---|---|---|---|
| Q-01 Studs, 9 ft | $4,104.00 (432 ea at $9.50) | Affected | $5,097.60 (432 ea at $11.80) | +$993.60 |
| Q-02 Plates become track | $2,268.00 (108 ea at $21.00) | Affected | $1,324.80 (72 ea at $18.40) | -$943.20 |
| Q-03 Window opening framing | $1,368.00 (36 set at $38.00) | Unresolved | not stated | open |
| Q-04 Fasteners, framing and sheathing | $630.00 (36 panel at $17.50) | Unresolved | not stated | open |
| Q-05 OSB sheathing, 7/16 in | $2,592.00 (108 sheet at $24.00) | Unchanged | $2,592.00 | no change |
| Q-06 Cavity insulation | $2,592.00 (36 panel at $72.00) | Affected | $2,808.00 (36 panel at $78.00) | +$216.00 |
| Q-07 Water-resistive barrier (WRB) membrane and tape | $936.00 (36 panel at $26.00) | Unchanged | $936.00 | no change |
| Q-08 Window units W-3 | $14,760.00 (36 ea at $410.00) | Unchanged | $14,760.00 | no change |
| Q-09 Window jamb extension kit (new line) | not in the baseline | Unresolved | not stated | open |
| Q-10 Packaging and shipping protection | $540.00 (36 panel at $15.00) | Unchanged | $540.00 | no change |
| Q-11 Factory labour allowance | $5,940.00 (108 h at $55.00) | Unresolved | not stated | open |
The resolved lines nearly cancel each other, and that's the number to refuse. It would be easy to read +$266.40 as the switch being close to cost-neutral, and it would mean nothing, because labour, fasteners, opening framing and a possible window kit are all still open. Amounts on affected lines come from a budget sheet that is valid for 14 days and not firm.
Who holds what, and who decides
Every unresolved item points at a missing input, and every missing input has a holder. That turns “we're not sure” into a short list of requests somebody can actually make. When an input gets a new revision, only the items that depend on it reopen; everything else keeps its status.
Missing inputs · 6
- U-1 Track leg height. Held by procurement, asking the steel supplier. A leg height for the 600T150-43 track, so overall panel height can be stated. Unblocks S-5.
- U-2 Opening-framing members and sizes. Held by the engineer of record. A member list and sizes for the window opening, so the line can be priced and the panel weighed. Unblocks Q-03, S-4.
- U-3 Fastening schedule. Held by the engineer of record. Screw type, spacing and count, with spacing and edge-distance values the inspection can check. Unblocks Q-04, Q-11, P-2.
- U-4 Window frame fit for a 6-inch wall. Held by the window supplier, asked through the estimator. Whether the standard frame covers a wall half an inch thicker, or an extension kit is needed. Unblocks Q-09, S-3.
- U-5 Measured steel cycle time, changeover and rework history at Line 2. Held by the plant manager. A trial build, or a measured estimate from a comparable line. Unblocks Q-11, P-1, P-3.
- U-6 Base anchorage detail for steel track. Held by the engineer of record. An anchor type and spacing for the steel track at the slab edge. Unblocks S-1.
Decisions · 6
- D-1 Is steel acceptable for WP-200 at 16 in centres? Decided by the engineer of record. Structural equivalence, opening framing, fastening and anchorage. Fire, thermal and acoustic performance are outside this example.
- D-2 Which stud depth, and can it ship in the window? Decided by the project manager (change owner), with procurement. This is the disputed assumption A-2.
- D-3 Can Line 2 build steel panels, and at what cycle? Decided by the plant manager. Jig, screw tools, changeover and rework allowance.
- D-4 What does inspection accept, and where does hold point H-1 sit? Decided by the quality lead, with the engineer of record. Acceptance values come from the fastening schedule.
- D-5 Do the site interfaces still work? Decided by the contractor's site superintendent, with the engineer of record. Anchorage, window fit, pick weight and top-of-wall elevation.
- D-6 What do we quote? Decided by the commercial lead. Blocked by hold point H-1. This packet commits no price.
Hold points · 4
- H-1 Before quote re-issue. Blocked while any quote line is unresolved and not carried as a stated exclusion.
- H-2 Before shop-drawing release. Blocked until D-1 is recorded against a named revision.
- H-3 Before start of steel production. Blocked until D-3 and D-4 are recorded.
- H-4 Before shipping. Blocked until D-5 confirms S-1, S-3, S-4 and S-5.
Try it yourself
Call each item Affected, Unchanged or Unresolved before you look, then open the key and check your call. It uses the case as quoted, with the 6-inch steel stud.
1. OSB sheathing, 7/16 in. Same board on every panel.
Check the key
Q-05 OSB sheathing, 7/16 in: Unchanged. Same board, same size, same layout. How it is fastened is carried in Q-04.
2. The studs themselves, 432 of them.
Check the key
Q-01 Studs, 9 ft: Affected. Timber studs become 600S162-43 steel studs. Price is from the vendor's budget sheet: indicative, valid 14 days, not firm.
3. Cavity insulation, a 5½-inch mineral wool batt in every panel.
Check the key
Q-06 Cavity insulation: Affected. The cavity is now 6 inches deep, not 5½. A 5½-inch batt would leave a half-inch gap, so the line moves to a 6-inch batt.
4. The 36 window units, W-3.
Check the key
Q-08 Window units W-3: Unchanged. Same unit, same size, same position (A-3). Whether it fits a thicker wall is a separate question: see S-3.
5. Whether the window frame and flashing still fit the wall.
Check the key
S-3 Window rough opening and flashing fit: Unresolved. The wall is half an inch thicker, so the window frame depth and the flashing build-up need a check. The missing input is U-4, held by the window supplier, asked through the estimator.
6. Top-of-wall elevation, where the floor cassette bears.
Check the key
S-5 Top-of-wall elevation and floor-cassette bearing: Unresolved. Overall panel height needs the track leg height, and the vendor sheet leaves it out. That makes it a missing input, and it should never be read as zero. The missing input is U-1, held by procurement, asking the steel supplier.
7. Fasteners for framing and sheathing.
Check the key
Q-04 Fasteners, framing and sheathing: Unresolved. Screws replace nails. The unit price is on the vendor sheet, but the fastening schedule (type, spacing, count) has not been issued, so the quantity is unknown. The missing input is U-3, held by the engineer of record.
8. Setup and cycle time for framing and sheathing on Line 2.
Check the key
P-1 Setup, framing and sheathing cycle: Unresolved. Steel needs a different jig and screw tools, and Line 2 has no measured steel cycle time or changeover. The missing input is U-5, held by the plant manager.
The challenge
The request says steel is a one-for-one drop-in at the same panel thickness. Do you accept it, reject it, or hold it until there is evidence? Then say who decides.
Check the key
Hold it. The drop-in claim is not established, because the quoted steel web is 6 inches and a 2x6 is 5½ inches deep in fact. The decision is D-2, and the project manager owns it as the change owner. Revising it changes or reopens 7 of 21 items and leaves 14 standing.
Your own challenge
Four things are left out on purpose. If your job needs one of them, add it and say which line it would touch.
- Thermal, fire and acoustic performance of the steel wall.
- Mechanical, electrical and plumbing (MEP) routing through steel studs, such as punch-outs and penetrations.
- Engineering and drafting hours for the revision.
- Freight, margin and tax.
About this example
Everything here is invented: the project, the plant, both suppliers, the drawings, the prices and the hours. It was built by hand from one data set, and every count and amount on this page is computed from it.